Click or drag to resize

clsImportProjectPlanningCalendar Property

ID form the calendar for the planning. The planning calendar is used to calculate from a planning demand x days and the resource quantity y the plan dates. The calendar defines the working days and hours. If empty, the planning calendar from the basic settings (by project business unit) is used.

Namespace:  MARIInterface
Assembly:  MARIInterface (in MARIInterface.dll) Version: 8.1.0.108
Syntax
public int PlanningCalendar { get; set; }

Property Value

Type: Int32
Remarks

MPProjektstamm.PlanungsKalender type: INT length: 4

View: MARIProjectMaster.PlanningCalendar: :Table: MPProjektstamm.PlanungsKalender

Linked Field: View: MARICalendar.CalendarID: :Table: MPKalender.KalenderID Calendar Management: Calendar Header

See Also